Recently, due to traffic and other factors, the supply of sand cement in the market is tight and the price increases greatly. In view of this, many home decoration companies began to promote the use of ceramic tile adhesives to replace cement mortar paving, the so-called thin paste method. However, many owners are confused about this. What is thin pasting method and how is it different from the traditional cement mortar paving method? Today, we invite experts to show you the process and difference between the two
brick laying preparation stage: whether the new thin pasting method or the traditional paving method, the wall needs to be treated and roughened first
step 1: base course inspection and treatment: different base course walls have different treatment methods. Shear wall, i.e. reinforced concrete cast-in-place wall, requires surface chiseling and hemp treatment. Wang Yan, manager of Dongyirisheng Engineering Department, said that because there are many film removers on the surface, it is easy to cause the bulge problem between the wall and the plastering and leveling layer; If it is a masonry plastered wall, it is necessary to judge whether the plastering layer on the surface of the wall is hollowed out. If it is hollowed out, it is necessary to repair it first; If it is a light partition wall, it needs to be hung with nets according to the firmness of the wall, so as to ensure the strength and prevent cracking
the second step of roughening: After wetting the wall, roughen the wetted wall with cement and 108 glue
traditional tiling method
tiling method using cement mortar as binder. Compared with the thin pasting method, the traditional paving method has less process of leveling the wall surface. After the wall surface is roughened, the tiles can be paved
the first step: mix the cement sand with water after dry mixing according to the ratio of cement sand 1:2.5. Apply cement mortar on the back of the soaked tiles, and then stick the tiles on the wet wall that has been roughened, and then pave them in turn. After the tiles are put on the wall, no major adjustment can be made. If the tiles are removed, the old cement mortar can be scraped off and repainted before paving
the second step of water supply curing: in order to ensure the combination of cement mortar and walls and bricks, after laying bricks, ensure water supply curing twice a day in the morning and evening (that is, spray an appropriate amount of water on the wall bricks), and generally the acceptance can be carried out after three days
thin paste process paving method
ceramic tile paving method using ceramic tile adhesive as the main bonding material. In terms of technology, the wall surface should be leveled first; Ceramic tile adhesive is used instead of traditional cement mortar as the adhesive between wall and ceramic tile